↑ THE HEADLINE · WEEK 20
CriticalBehind plan; corrective actions in progress. Project tracks -5.63% against revised baseline; forecast handover slips by 20 days.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
Jul 8, 2026
FORECAST
Jul 28, 2026
BEHIND TARGET
+20 days
vs current 14-day pace
DAYS TO HANDOVER
0of 250 program-days
PROGRESS
94.4%
-5.63%
vs 100.0% planned
VARIANCE
-5.63%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
50,132
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 94%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
24/33
CREW
Weather + crew
Partly Cloudy, 31°C
31°
Partly Cloudy · Hum Very High · Wind 18 km/h
RAIN-DAYS · JUL
3 rain days this month
CREW ON SITE
72% staffed
24of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 24 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 98.53%)
Slope Protection
tgt 100%89%-11.46%
28th Street - Trimming, Drilling, Wiremesh Installation, Shotcreting, Soil Nail Installation, Grouting, Plate Locking
Dewatering
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 8
DPR-BGC_LUX-2026-054
100.00%
94.37%
-5.63%
Behind
›
Jul 7
DPR-BGC_LUX-2026-053
100.00%
94.19%
-5.81%
Behind
›
Jul 7
DPR-BGC_LUX-2026-052
100.00%
94.15%
-5.85%
Behind
›
Jul 6
DPR-BGC_LUX-2026-051
100.00%
93.91%
-6.09%
Behind
›
Jul 4
DPR-BGC_LUX-2026-050
100.00%
93.66%
-6.34%
Behind
›
Jul 3
DPR-BGC_LUX-2026-050
100.00%
93.24%
-6.76%
Behind
›
Jul 2
DPR-BGC_LUX-2026-049
100.00%
92.98%
-7.02%
Behind
›
From site, today
7 photos · Wed Jul 8 report
SITE PHOTO
Bulk excavation · Retail Block · 8m depth
SITE PHOTO
Slope protection — 26th St berm
SITE PHOTO
Drilling works — 5th Ave
SITE PHOTO
Dust control checkpoint
SITE PHOTO
Wiremesh installation
SITE PHOTO
Shotcreting · berm face
SITE PHOTO
Safety railing install