↑ THE HEADLINE · WEEK 40
WatchBehind plan; corrective actions in progress. Project tracks -1.93% against revised baseline; forecast handover slips by 30 days.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Jul 28, 2026
BEHIND TARGET
+30 days
vs current 14-day pace
DAYS OVER TARGET
23of 250 program-days
PROGRESS
98.1%
-1.93%
vs 100.0% planned
VARIANCE
-1.93%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
53,332
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 98%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
18/33
CREW
Weather + crew
Heavy Rain, 32°C
32°
Heavy Rain · Hum Very High · Wind 15 km/h
RAIN-DAYS · JUL
7 rain days this month
CREW ON SITE
54% staffed
18of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 18 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 99.61%)
Slope Protection
tgt 100%97%-3.12%
5th Avenue - Trimming, Space Truss Installation
28th - Wiremesh Installation, Shotcreting
Berm - Trimming
Dewatering
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 21
DPR-BGC_LUX-2026-055
100.00%
98.07%
-1.93%
Watch
›
Jul 20
DPR-BGC_LUX-2026-054
100.00%
97.64%
-2.36%
Behind
›
Jul 18
DPR-BGC_LUX-2026-053
100.00%
97.45%
-2.55%
Behind
›
Jul 17
DPR-BGC_LUX-2026-056
100.00%
97.10%
-2.90%
Behind
›
Jul 16
DPR-BGC_LUX-2026-055
100.00%
96.73%
-3.27%
Behind
›
Jul 15
DPR-BGC_LUX-2026-054
100.00%
96.54%
-3.46%
Behind
›
Jul 14
DPR-BGC_LUX-2026-053
100.00%
96.29%
-3.71%
Behind
›
From site, today
8 photos · Tue Jul 21 report

Trimmed Area along Berm

Shotcrete Area along 28th

Slope Protection and Excavated Area along 28th

Slope Protection and Excavated Area along 5th

Excavated Area along 5th cor 28th

Excavated Area along 5th cor 26th

Safety railing install