LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
22:06 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 45
Watch
Behind plan; corrective actions in progress. Project tracks -0.74% against revised baseline; forecast handover slips by 86 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.

Substructure phase99% completeDay 311 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Sep 22, 2026
BEHIND TARGET
+86 days
vs current 14-day pace
DAYS OVER TARGET
61of 250 program-days
PROGRESS
99.3%
-0.74%
vs 100.0% planned
VARIANCE
-0.74%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
56,966
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
95%100%Jul 25Aug 6Aug 18Aug 28
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 99%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
11/33
CREW
Weather + crew
Heavy Rain, 27°C
27°
Heavy Rain · Hum Very High · Wind 34 km/h
RAIN-DAYS · AUG
19 rain days this month
CREW ON SITE
33% staffed
11of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 11 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 99.76%)
Slope Protection
tgt 100%100%-0.20%
5th Ave - Plate Locking
Dewatering - 4 discharge pumps & 1 back-up
Soil Transfer to Interim Parking
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Aug 28
DPR-BGC_LUX-2026-069
100.00%
99.26%
-0.74%
Watch
Aug 27
DPR-BGC_LUX-2026-068
100.00%
99.25%
-0.75%
Watch
Aug 26
DPR-BGC_LUX-2026-067
100.00%
99.25%
-0.75%
Watch
Aug 25
DPR-BGC_LUX-2026-066
100.00%
99.25%
-0.75%
Watch
Aug 24
DPR-BGC_LUX-2026-064
100.00%
99.25%
-0.75%
Watch
Aug 22
DPR-BGC_LUX-2026-065
100.00%
99.17%
-0.83%
Watch
Aug 21
DPR-BGC_LUX-2026-068
100.00%
99.09%
-0.91%
Watch
From site, today
10 photos · Fri Aug 28 report
Pull-out Test at 5th
Pull-out Test at 5th
Dewatering Setup
Dewatering Setup
Soil for haul out
Soil for haul out
Excavated Area along 5th cor 26th
Excavated Area along 5th cor 26th
Excavated Area along 5th cor 28th
Excavated Area along 5th cor 28th
Shotcreting · berm face
Shotcreting · berm face
Safety railing install
Safety railing install