↑ THE HEADLINE · WEEK 20
Behind
Behind plan; corrective actions in progress. Project tracks -2.90% against revised baseline; forecast handover pending data.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.

Substructure phase97% completeDay 269 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
FORECAST
FORECAST
vs current 14-day pace
DAYS TO HANDOVER
0of 250 program-days
PROGRESS
97.1%
-2.90%
vs 100.0% planned
VARIANCE
-2.90%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
51,532
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
85%90%95%100%Jun 15Jun 26Jul 7Jul 17
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 97%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
18/33
CREW
Weather + crew
Clear, 31°C
31°
Clear · Hum Very High · Wind 19 km/h
RAIN-DAYS · JUL
6 rain days this month
CREW ON SITE
54% staffed
18of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 18 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 99.13%)
Slope Protection
tgt 100%95%-5.01%
28th - Drilling, Wiremesh Installation, Shotcreting, Soil Nail Installation, Grouting, Plate Locking
Berm - Trimming
Dewatering
Hualing and Disposal
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 17
DPR-BGC_LUX-2026-056
100.00%
97.10%
-2.90%
Behind
Jul 16
DPR-BGC_LUX-2026-055
100.00%
96.73%
-3.27%
Behind
Jul 15
DPR-BGC_LUX-2026-054
100.00%
96.54%
-3.46%
Behind
Jul 14
DPR-BGC_LUX-2026-053
100.00%
96.29%
-3.71%
Behind
Jul 13
DPR-BGC_LUX-2026-052
100.00%
95.82%
-4.18%
Behind
Jul 11
DPR-BGC_LUX-2026-053
100.00%
95.56%
-4.44%
Behind
Jul 10
DPR-BGC_LUX-2026-052
100.00%
95.05%
-4.95%
Behind
From site, today
4 photos · Fri Jul 17 report
Excavated Area 5th cor 26th
Excavated Area 5th cor 26th
Shotcrete and Drilling Works at 28th
Shotcrete and Drilling Works at 28th
Excavated Area 5th
Excavated Area 5th
Dewatering Works at 5th
Dewatering Works at 5th
SITE PHOTO
Wiremesh installation
SITE PHOTO
Shotcreting · berm face
SITE PHOTO
Safety railing install