LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
20:17 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 20
Watch
Behind plan; corrective actions in progress. Project tracks -1.37% against revised baseline; forecast handover slips by 6 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: 2nd Shotcrete Group not yet remobilized. Zero safety incidents this week.

Substructure phase75% completeDay 210 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jun 24, 2026
FORECAST
Jun 30, 2026
BEHIND TARGET
+6 days
vs current 14-day pace
DAYS TO HANDOVER
40of 250 program-days
PROGRESS
74.6%
-1.37%
vs 76.0% planned
VARIANCE
-1.37%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 5 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
5
Safety Railing
SAFETY
Safety Manhours
THIS WK
1,700
PTD
37,668
8-hour workday + Overtime
SAFETY
NCRs Issued
THIS WK
0
PTD
4
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
5
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
50%55%60%65%70%75%80%BASELINE V2Apr 15Apr 27May 8May 19
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
⚠ ILLUSTRATIVE · WAITING ON MASTER SCHEDULE
TODAY · 75%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
22/33
CREW
Weather + crew
Partly Cloudy, 32°C
32°
Partly Cloudy · Hum High · Wind 16 km/h
RAIN-DAYS · MAY
0 rain days this month
CREW ON SITE
66% staffed
22of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 22 on site
Bulk Excavation of Retail Block (8 meters depth) [Target: 82.09%; Actual: 93.92%)
Slope Protection
tgt 67%49%-18.09%
5th Avenue - Trimming
Berm - Trimming, Wiremesh Installation, Shotcreting
Material Testing
Risks + open items
Watch-list
2nd Shotcrete Group not yet remobilized.
Watch · open
NCRs open
4
RFIs pending
0
QA / QC open
1
LSB-NCR-WECI-004-004
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
May 19
DPR-BGC_LUX-2026-015
75.98%
74.61%
-1.37%
Watch
May 18
DPR-BGC_LUX-2026-014
75.31%
74.81%
-0.50%
Watch
May 16
DPR-BGC_LUX-2026-013
74.03%
74.43%
+0.40%
On Track
May 15
DPR-BGC_LUX-2026-012
73.35%
73.96%
+0.61%
On Track
May 14
DPR-BGC_LUX-2026-011
72.67%
73.21%
+0.54%
On Track
May 13
DPR-BGC_LUX-2026-010
71.98%
72.42%
+0.44%
On Track
May 12
DPR-BGC_LUX-2026-008
71.30%
71.63%
+0.33%
On Track
From site, today
10 photos · Tue May 19 report
Excavated Area
Excavated Area
Excavation Along Berm 28th Street
Excavation Along Berm 28th Street
Excavated Area along 28th Street
Excavated Area along 28th Street
Hauling and Disposal
Hauling and Disposal
Excavated Area along 26th Street
Excavated Area along 26th Street
Excavation Works
Excavation Works
Safety railing install
Safety railing install