LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
15:07 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 47
Watch
Behind plan; corrective actions in progress. Project tracks -0.70% against revised baseline; forecast handover slips by 339 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.

Substructure phase99% completeDay 326 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Jun 2, 2027
BEHIND TARGET
+339 days
vs current 14-day pace
DAYS OVER TARGET
76of 250 program-days
PROGRESS
99.3%
-0.70%
vs 100.0% planned
VARIANCE
-0.70%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
57,988
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
95%100%Aug 10Aug 21Sep 2Sep 12
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 99%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
9/33
CREW
Weather + crew
Light Rain, 29°C
29°
Light Rain · Hum Very High · Wind 14 km/h
RAIN-DAYS · SEP
9 rain days this month
CREW ON SITE
27% staffed
9of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 9 on site
Bulk Excavation of Retail Block (10 meters depth)
tgt 100%100%-0.24%
Slope Protection
tgt 100%100%-0.10%
Hauling (134.545 cubic meters)
Horizontal Trimming
Dewatering - 5 discharge pumps
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Sep 12
DPR-BGC_LUX-2026-013
100.00%
99.30%
-0.70%
Watch
Sep 11
DPR-BGC_LUX-2026-012
100.00%
99.30%
-0.70%
Watch
Sep 10
DPR-BGC_LUX-2026-011
100.00%
99.30%
-0.70%
Watch
Sep 9
DPR-BGC_LUX-2026-010
100.00%
99.30%
-0.70%
Watch
Sep 8
DPR-BGC_LUX-2026-009
100.00%
99.30%
-0.70%
Watch
Sep 7
DPR-BGC_LUX-2026-008
100.00%
99.30%
-0.70%
Watch
Sep 5
DPR-BGC_LUX-2026-007
100.00%
99.30%
-0.70%
Watch
From site, today
10 photos · Sat Sep 12 report
Excavated Area at 5th cor 26th
Excavated Area at 5th cor 26th
Berm at 26th
Berm at 26th
Excavated Area at 5th
Excavated Area at 5th
Dewatering Setup
Dewatering Setup
Excavated Area at Slope Protection at 5th cor 28th
Excavated Area at Slope Protection at 5th cor 28th
Shotcreting · berm face
Shotcreting · berm face
Safety railing install
Safety railing install