LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
12:05 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 20
Behind
Behind plan; corrective actions in progress. Project tracks -4.95% against revised baseline; forecast handover slips by 17 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.

Substructure phase95% completeDay 262 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jul 10, 2026
FORECAST
Jul 27, 2026
BEHIND TARGET
+17 days
vs current 14-day pace
DAYS TO HANDOVER
0of 250 program-days
PROGRESS
95.0%
-4.95%
vs 100.0% planned
VARIANCE
-4.95%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
50,132
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
80%85%90%95%100%Jun 8Jun 19Jul 1Jul 10
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 95%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
23/33
CREW
Weather + crew
Heavy Rain, 29°C
29°
Heavy Rain · Hum Very High · Wind 27 km/h
RAIN-DAYS · JUL
4 rain days this month
CREW ON SITE
69% staffed
23of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 23 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 98.93%)
Slope Protection
tgt 100%90%-9.99%
28th - Drilling, Trimming, Wiremesh Installation, Shotcreting, Soil Nail Installation, Grouting, Plate Locking
5th Avenue - Space Truss Installation
Dewatering
Hauling and Disposal
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 10
DPR-BGC_LUX-2026-052
100.00%
95.05%
-4.95%
Behind
Jul 9
DPR-BGC_LUX-2026-051
100.00%
94.70%
-5.30%
Behind
Jul 8
DPR-BGC_LUX-2026-054
100.00%
94.37%
-5.63%
Behind
Jul 7
DPR-BGC_LUX-2026-053
100.00%
94.19%
-5.81%
Behind
Jul 7
DPR-BGC_LUX-2026-052
100.00%
94.15%
-5.85%
Behind
Jul 6
DPR-BGC_LUX-2026-051
100.00%
93.91%
-6.09%
Behind
Jul 4
DPR-BGC_LUX-2026-050
100.00%
93.66%
-6.34%
Behind
From site, today
6 photos · Fri Jul 10 report
Dewatering
Dewatering
Excavated Area at 5th and 26th
Excavated Area at 5th and 26th
Excavated Area at 5th
Excavated Area at 5th
Excavated Area at 5th and 28th
Excavated Area at 5th and 28th
Drilling at 28th
Drilling at 28th
Soil Pulling at 28th
Soil Pulling at 28th
SITE PHOTO
Safety railing install