↑ THE HEADLINE · WEEK 45
WatchBehind plan; corrective actions in progress. Project tracks -0.74% against revised baseline; forecast handover slips by 86 days.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Sep 22, 2026
BEHIND TARGET
+86 days
vs current 14-day pace
DAYS OVER TARGET
61of 250 program-days
PROGRESS
99.3%
-0.74%
vs 100.0% planned
VARIANCE
-0.74%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
56,966
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 99%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
11/33
CREW
Weather + crew
Heavy Rain, 27°C
27°
Heavy Rain · Hum Very High · Wind 34 km/h
RAIN-DAYS · AUG
19 rain days this month
CREW ON SITE
33% staffed
11of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 11 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 99.76%)
Slope Protection
tgt 100%100%-0.20%
5th Ave - Plate Locking
Dewatering - 4 discharge pumps & 1 back-up
Soil Transfer to Interim Parking
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Aug 28
DPR-BGC_LUX-2026-069
100.00%
99.26%
-0.74%
Watch
›
Aug 27
DPR-BGC_LUX-2026-068
100.00%
99.25%
-0.75%
Watch
›
Aug 26
DPR-BGC_LUX-2026-067
100.00%
99.25%
-0.75%
Watch
›
Aug 25
DPR-BGC_LUX-2026-066
100.00%
99.25%
-0.75%
Watch
›
Aug 24
DPR-BGC_LUX-2026-064
100.00%
99.25%
-0.75%
Watch
›
Aug 22
DPR-BGC_LUX-2026-065
100.00%
99.17%
-0.83%
Watch
›
Aug 21
DPR-BGC_LUX-2026-068
100.00%
99.09%
-0.91%
Watch
›
From site, today
10 photos · Fri Aug 28 report

Pull-out Test at 5th

Dewatering Setup

Soil for haul out

Excavated Area along 5th cor 26th

Excavated Area along 5th cor 28th

Shotcreting · berm face

Safety railing install