↑ THE HEADLINE · WEEK 47
WatchBehind plan; corrective actions in progress. Project tracks -0.70% against revised baseline; forecast handover slips by 283 days.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Apr 7, 2027
BEHIND TARGET
+283 days
vs current 14-day pace
DAYS OVER TARGET
73of 250 program-days
PROGRESS
99.3%
-0.70%
vs 100.0% planned
VARIANCE
-0.70%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
57,988
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 99%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
10/33
CREW
Weather + crew
Heavy Rain, 28°C
28°
Heavy Rain · Hum Very High · Wind 19 km/h
RAIN-DAYS · SEP
6 rain days this month
CREW ON SITE
30% staffed
10of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 10 on site
Bulk Excavation of Retail Block (10 meters depth)
tgt 100%100%-0.24%
Slope Protection
tgt 100%100%-0.10%
Hauling (197.3 cubic meters)
Horizontal Trimming
Dewatering - 5 discharge pumps
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Sep 9
DPR-BGC_LUX-2026-010
100.00%
99.30%
-0.70%
Watch
›
Sep 8
DPR-BGC_LUX-2026-009
100.00%
99.30%
-0.70%
Watch
›
Sep 7
DPR-BGC_LUX-2026-008
100.00%
99.30%
-0.70%
Watch
›
Sep 5
DPR-BGC_LUX-2026-007
100.00%
99.30%
-0.70%
Watch
›
Sep 4
DPR-BGC_LUX-2026-006
100.00%
99.30%
-0.70%
Watch
›
Sep 3
DPR-BGC_LUX-2026-005
100.00%
99.30%
-0.70%
Watch
›
Sep 2
DPR-BGC_LUX-2026-004
100.00%
99.30%
-0.70%
Watch
›
From site, today
8 photos · Wed Sep 9 report

Horizontal Trimming

Dewatering Setup

Excavated Area at Slope Protection at 5th cor 28th

Excavated Area at 5th

Slope Protection at 28th

Shotcreting · berm face

Safety railing install