LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
15:05 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 46
Watch
Behind plan; corrective actions in progress. Project tracks -0.70% against revised baseline; forecast handover slips by 99 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.

Substructure phase99% completeDay 316 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Oct 5, 2026
BEHIND TARGET
+99 days
vs current 14-day pace
DAYS OVER TARGET
66of 250 program-days
PROGRESS
99.3%
-0.70%
vs 100.0% planned
VARIANCE
-0.70%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
57,466
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
95%100%Jul 30Aug 11Aug 22Sep 2
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 99%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
12/33
CREW
Weather + crew
Overcast, 29°C
29°
Overcast · Hum Very High · Wind 14 km/h
RAIN-DAYS · SEP
0 rain days this month
CREW ON SITE
36% staffed
12of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 12 on site
Bulk Excavation of Retail Block (10 meters depth)
tgt 100%100%-0.24%
Slope Protection
tgt 100%100%-0.10%
5th Ave - Plate Locking (Completed)
Dewatering - 5 discharge pumps
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Sep 2
DPR-BGC_LUX-2026-004
100.00%
99.30%
-0.70%
Watch
Sep 1
DPR-BGC_LUX-2026-003
100.00%
99.30%
-0.70%
Watch
Aug 31
DPR-BGC_LUX-2026-002
100.00%
99.27%
-0.73%
Watch
Aug 29
DPR-BGC_LUX-2026-001
100.00%
99.26%
-0.74%
Watch
Aug 28
DPR-BGC_LUX-2026-069
100.00%
99.26%
-0.74%
Watch
Aug 27
DPR-BGC_LUX-2026-068
100.00%
99.25%
-0.75%
Watch
Aug 26
DPR-BGC_LUX-2026-067
100.00%
99.25%
-0.75%
Watch
From site, today
8 photos · Wed Sep 2 report
Horizontal Trimming
Horizontal Trimming
Dewatering Setup
Dewatering Setup
Excavated Area at 5th cor 26th
Excavated Area at 5th cor 26th
Berm at 26th
Berm at 26th
Wiremesh installation
Wiremesh installation
Shotcreting · berm face
Shotcreting · berm face
Safety railing install
Safety railing install