LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
16:47 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 41
Watch
Behind plan; corrective actions in progress. Project tracks -1.72% against revised baseline; forecast handover slips by 40 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.

Substructure phase98% completeDay 280 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Aug 7, 2026
BEHIND TARGET
+40 days
vs current 14-day pace
DAYS OVER TARGET
30of 250 program-days
PROGRESS
98.3%
-1.72%
vs 100.0% planned
VARIANCE
-1.72%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
54,782
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
90%95%100%Jun 25Jul 7Jul 17Jul 28
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 98%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
19/33
CREW
Weather + crew
Light Rain, 30°C
30°
Light Rain · Hum Very High · Wind 6 km/h
RAIN-DAYS · JUL
12 rain days this month
CREW ON SITE
57% staffed
19of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 19 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 99.62%)
Slope Protection
tgt 100%97%-2.58%
5th Avenue - Trimming, Wiremesh Installation
28th - Wiremesh Installation, Shotcreting, Plate Locking
Dewatering
Demolition of Underground Structures
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 28
DPR-BGC_LUX-2026-059
100.00%
98.28%
-1.72%
Watch
Jul 27
DPR-BGC_LUX-2026-058
100.00%
98.23%
-1.77%
Watch
Jul 25
DPR-BGC_LUX-2026-059
100.00%
98.18%
-1.82%
Watch
Jul 24
DPR-BGC_LUX-2026-058
100.00%
98.15%
-1.85%
Watch
Jul 23
DPR-BGC_LUX-2026-057
100.00%
98.14%
-1.86%
Watch
Jul 22
DPR-BGC_LUX-2026-056
100.00%
98.11%
-1.89%
Watch
Jul 21
DPR-BGC_LUX-2026-055
100.00%
98.07%
-1.93%
Watch
From site, today
6 photos · Tue Jul 28 report
Dewatering Setup
Dewatering Setup
Excavated Area at 5th cor 28th
Excavated Area at 5th cor 28th
Excavated Area at 5th
Excavated Area at 5th
Excavated Area at 5th cor 26th
Excavated Area at 5th cor 26th
Shotcrete and Soil Pulling at 28th
Shotcrete and Soil Pulling at 28th
Emergency Dewatering connection at 5th
Emergency Dewatering connection at 5th
SITE PHOTO
Safety railing install