LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
13:05 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 20
Behind
Behind plan; corrective actions in progress. Project tracks -3.84% against revised baseline; forecast handover slips by 15 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; Zero safety incidents this week.

Substructure phase87% completeDay 235 / 250
FORECAST · COMPLETION
TARGET
Jun 29, 2026
FORECAST
Jul 14, 2026
BEHIND TARGET
+15 days
vs current 14-day pace
DAYS TO HANDOVER
15of 250 program-days
PROGRESS
86.8%
-3.84%
vs 90.7% planned
VARIANCE
-3.84%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 6 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
6
For Closing
QUALITY
NCRs Issued
THIS WK
0
PTD
4
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
5
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
SAFETY
Safety Manhours
THIS WK
1,550
PTD
44,268
8-hour workday
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
70%75%80%85%90%95%BASELINE V2May 12May 23Jun 3Jun 13
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
⚠ ILLUSTRATIVE · WAITING ON MASTER SCHEDULE
TODAY · 87%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
29/33
CREW
Weather + crew
Clear, 32°C
32°
Clear · Hum Very High · Wind 14 km/h
RAIN-DAYS · JUN
4 rain days this month
CREW ON SITE
87% staffed
29of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 29 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 96.09%; Actual: 97.51%)
Slope Protection
tgt 87%74%-12.99%
5th Avenue - Soil Nail Installation
26th - Trimming, Drilling, Wiremesh Installation, Shotcreting, Plate Locking
28th Street - Wiremesh Installation, Shotcreting, Soil Nail Installation, Grouting
Dewatering
Risks + open items
Watch-list
No delays reported.
NCRs open
4
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jun 13
DPR-BGC_LUX-2026-037
90.67%
86.83%
-3.84%
Behind
Jun 12
DPR-BGC_LUX-2026-036
89.93%
86.39%
-3.54%
Behind
Jun 11
DPR-BGC_LUX-2026-035
89.20%
85.96%
-3.24%
Behind
Jun 10
DPR-BGC_LUX-2026-035
88.47%
85.62%
-2.85%
Behind
Jun 9
DPR-BGC_LUX-2026-034
87.74%
85.04%
-2.70%
Behind
Jun 8
DPR-BGC_LUX-2026-033
87.00%
84.36%
-2.64%
Behind
Jun 6
DPR-BGC_LUX-2026-032
85.54%
83.80%
-1.74%
Watch
From site, today
7 photos · Sat Jun 13 report
SITE PHOTO
Bulk excavation · Retail Block · 8m depth
SITE PHOTO
Slope protection — 26th St berm
SITE PHOTO
Drilling works — 5th Ave
SITE PHOTO
Dust control checkpoint
SITE PHOTO
Wiremesh installation
SITE PHOTO
Shotcreting · berm face
SITE PHOTO
Safety railing install