LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
13:05 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 20
Watch
Behind plan; corrective actions in progress. Project tracks -1.74% against revised baseline; forecast handover slips by 1 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; Zero safety incidents this week.

Substructure phase84% completeDay 228 / 250
FORECAST · COMPLETION
TARGET
Jul 5, 2026
FORECAST
Jul 6, 2026
BEHIND TARGET
+1 days
vs current 14-day pace
DAYS TO HANDOVER
22of 250 program-days
PROGRESS
83.8%
-1.74%
vs 85.5% planned
VARIANCE
-1.74%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 5 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
5
Closed
QUALITY
NCRs Issued
THIS WK
0
PTD
4
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
5
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
SAFETY
Safety Manhours
THIS WK
1,350
PTD
42,918
8-hour workday
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
65%70%75%80%85%90%BASELINE V2May 5May 16May 27Jun 6
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
⚠ ILLUSTRATIVE · WAITING ON MASTER SCHEDULE
TODAY · 84%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
25/33
CREW
Weather + crew
Heavy Rain, 31°C
31°
Heavy Rain · Hum Very High · Wind 15 km/h
RAIN-DAYS · JUN
4 rain days this month
CREW ON SITE
75% staffed
25of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 25 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 93.27%; Actual: 97.11%)
Slope Protection
tgt 72%67%-4.60%
26th - Shotcreting
28th Street - Shotcreting
5th Avenue - Trimming, Drilling
Berm - Shotcreting
Risks + open items
Watch-list
No delays reported.
NCRs open
4
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jun 6
DPR-BGC_LUX-2026-032
85.54%
83.80%
-1.74%
Watch
Jun 5
DPR-BGC_LUX-2026-031
87.62%
83.16%
-4.46%
Behind
Jun 4
DPR-BGC_LUX-2026-030
86.81%
82.66%
-4.15%
Behind
Jun 3
DPR-BGC_LUX-2026-029
86.00%
82.13%
-3.87%
Behind
Jun 2
DPR-BGC_LUX-2026-028
85.19%
81.65%
-3.54%
Behind
Jun 1
DPR-BGC_LUX-2026-027
84.39%
81.32%
-3.07%
Behind
May 30
DPR-BGC_LUX-2026-026
82.67%
80.88%
-1.79%
Watch
From site, today
9 photos · Sat Jun 6 report
Slope Protection along Ramp
Slope Protection along Ramp
Slope Protection along 5th
Slope Protection along 5th
Excavated Area for Dewatering
Excavated Area for Dewatering
Trimming along 5th
Trimming along 5th
Excavated Area view from 28th
Excavated Area view from 28th
Slope Protection along 28th
Slope Protection along 28th
Safety railing install
Safety railing install