↑ THE HEADLINE · WEEK 40
WatchBehind plan; corrective actions in progress. Project tracks -1.82% against revised baseline; forecast handover slips by 36 days.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Aug 3, 2026
BEHIND TARGET
+36 days
vs current 14-day pace
DAYS OVER TARGET
27of 250 program-days
PROGRESS
98.2%
-1.82%
vs 100.0% planned
VARIANCE
-1.82%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
53,332
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 98%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block99.6%
Slope Protection (5th / 26th)95.8%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
19/33
CREW
Weather + crew
Light Rain, 27°C
27°
Light Rain · Hum Very High · Wind 37 km/h
RAIN-DAYS · JUL
10 rain days this month
CREW ON SITE
57% staffed
19of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 19 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 99.62%)
Slope Protection
tgt 100%97%-2.85%
5th Avenue - Trimming
28th - Wiremesh Installation, Shotcreting, Plate Locking
Dewatering
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 25
DPR-BGC_LUX-2026-059
100.00%
98.18%
-1.82%
Watch
›
Jul 24
DPR-BGC_LUX-2026-058
100.00%
98.15%
-1.85%
Watch
›
Jul 23
DPR-BGC_LUX-2026-057
100.00%
98.14%
-1.86%
Watch
›
Jul 22
DPR-BGC_LUX-2026-056
100.00%
98.11%
-1.89%
Watch
›
Jul 21
DPR-BGC_LUX-2026-055
100.00%
98.07%
-1.93%
Watch
›
Jul 20
DPR-BGC_LUX-2026-054
100.00%
97.64%
-2.36%
Behind
›
Jul 18
DPR-BGC_LUX-2026-053
100.00%
97.45%
-2.55%
Behind
›
From site, today
7 photos · Sat Jul 25 report

Excavated Area at 26th

Excavated Area at 5th

Excavated Area at 28th

Slope Protection at 28th

Horizontal Trimming

Ramp Condition

Safety railing install