LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
09:23 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 20
Critical
Behind plan; corrective actions in progress. Project tracks -5.63% against revised baseline; forecast handover slips by 20 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.

Substructure phase94% completeDay 260 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jul 8, 2026
FORECAST
Jul 28, 2026
BEHIND TARGET
+20 days
vs current 14-day pace
DAYS TO HANDOVER
0of 250 program-days
PROGRESS
94.4%
-5.63%
vs 100.0% planned
VARIANCE
-5.63%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
50,132
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
80%85%90%95%100%BASELINE V2Jun 5Jun 17Jun 29Jul 8
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 94%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
24/33
CREW
Weather + crew
Partly Cloudy, 31°C
31°
Partly Cloudy · Hum Very High · Wind 18 km/h
RAIN-DAYS · JUL
3 rain days this month
CREW ON SITE
72% staffed
24of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 24 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 98.53%)
Slope Protection
tgt 100%89%-11.46%
28th Street - Trimming, Drilling, Wiremesh Installation, Shotcreting, Soil Nail Installation, Grouting, Plate Locking
Dewatering
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 8
DPR-BGC_LUX-2026-054
100.00%
94.37%
-5.63%
Behind
Jul 7
DPR-BGC_LUX-2026-053
100.00%
94.19%
-5.81%
Behind
Jul 7
DPR-BGC_LUX-2026-052
100.00%
94.15%
-5.85%
Behind
Jul 6
DPR-BGC_LUX-2026-051
100.00%
93.91%
-6.09%
Behind
Jul 4
DPR-BGC_LUX-2026-050
100.00%
93.66%
-6.34%
Behind
Jul 3
DPR-BGC_LUX-2026-050
100.00%
93.24%
-6.76%
Behind
Jul 2
DPR-BGC_LUX-2026-049
100.00%
92.98%
-7.02%
Behind
From site, today
6 photos · Wed Jul 8 report
Dewatering
Dewatering
Excavated Area at 5th and 26th
Excavated Area at 5th and 26th
Excavated Area at 5th
Excavated Area at 5th
Excavated Area at 5th and 28th
Excavated Area at 5th and 28th
Drilling at 28th
Drilling at 28th
Soil Pulling at 28th
Soil Pulling at 28th
SITE PHOTO
Safety railing install