↑ THE HEADLINE · WEEK 20
BehindBehind plan; corrective actions in progress. Project tracks -4.44% against revised baseline; forecast handover slips by 12 days.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
Jul 11, 2026
FORECAST
Jul 23, 2026
BEHIND TARGET
+12 days
vs current 14-day pace
DAYS TO HANDOVER
0of 250 program-days
PROGRESS
95.6%
-4.44%
vs 100.0% planned
VARIANCE
-4.44%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
1,400
PTD
50,132
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 96%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
22/33
CREW
Weather + crew
Heavy Rain, 27°C
27°
Heavy Rain · Hum Very High · Wind 31 km/h
RAIN-DAYS · JUL
5 rain days this month
CREW ON SITE
66% staffed
22of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 22 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 98.83%)
Slope Protection
tgt 100%91%-8.64%
28th - Drilling, Trimming, Wiremesh Installation, Shotcreting, Soil Nail Installation, Grouting, Plate Locking
5th Avenue - Space Truss Installation
Dewatering
Hauling and Disposal
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 11
DPR-BGC_LUX-2026-053
100.00%
95.56%
-4.44%
Behind
›
Jul 10
DPR-BGC_LUX-2026-052
100.00%
95.05%
-4.95%
Behind
›
Jul 9
DPR-BGC_LUX-2026-051
100.00%
94.70%
-5.30%
Behind
›
Jul 8
DPR-BGC_LUX-2026-054
100.00%
94.37%
-5.63%
Behind
›
Jul 7
DPR-BGC_LUX-2026-053
100.00%
94.19%
-5.81%
Behind
›
Jul 7
DPR-BGC_LUX-2026-052
100.00%
94.15%
-5.85%
Behind
›
Jul 6
DPR-BGC_LUX-2026-051
100.00%
93.91%
-6.09%
Behind
›
From site, today
6 photos · Sat Jul 11 report

Dewatering

Excavated Area at 5th and 26th

Excavated Area at 5th

Excavated Area at 5th and 28th

Drilling at 28th

Soil Pulling at 28th
SITE PHOTO
Safety railing install