↑ THE HEADLINE · WEEK 20
BehindBehind plan; corrective actions in progress. Project tracks -2.90% against revised baseline; forecast handover pending data.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: LSB-NCR-WECI-007-007 - Space Truss and Weepholes Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
—
FORECAST
—
FORECAST
—
vs current 14-day pace
DAYS TO HANDOVER
0of 250 program-days
PROGRESS
97.1%
-2.90%
vs 100.0% planned
VARIANCE
-2.90%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 7 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
7
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
51,532
8-hour workday
SAFETY
NCRs Issued
THIS WK
0
PTD
6
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
8
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
TODAY · 97%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
18/33
CREW
Weather + crew
Clear, 31°C
31°
Clear · Hum Very High · Wind 19 km/h
RAIN-DAYS · JUL
6 rain days this month
CREW ON SITE
54% staffed
18of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 18 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 100.00%; Actual: 99.13%)
Slope Protection
tgt 100%95%-5.01%
28th - Drilling, Wiremesh Installation, Shotcreting, Soil Nail Installation, Grouting, Plate Locking
Berm - Trimming
Dewatering
Hualing and Disposal
Risks + open items
Watch-list
LSB-NCR-WECI-007-007 - Space Truss and Weepholes
Watch · open
NCRs open
6
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jul 17
DPR-BGC_LUX-2026-056
100.00%
97.10%
-2.90%
Behind
›
Jul 16
DPR-BGC_LUX-2026-055
100.00%
96.73%
-3.27%
Behind
›
Jul 15
DPR-BGC_LUX-2026-054
100.00%
96.54%
-3.46%
Behind
›
Jul 14
DPR-BGC_LUX-2026-053
100.00%
96.29%
-3.71%
Behind
›
Jul 13
DPR-BGC_LUX-2026-052
100.00%
95.82%
-4.18%
Behind
›
Jul 11
DPR-BGC_LUX-2026-053
100.00%
95.56%
-4.44%
Behind
›
Jul 10
DPR-BGC_LUX-2026-052
100.00%
95.05%
-4.95%
Behind
›
From site, today
4 photos · Fri Jul 17 report

Excavated Area 5th cor 26th

Shotcrete and Drilling Works at 28th

Excavated Area 5th

Dewatering Works at 5th
SITE PHOTO
Wiremesh installation
SITE PHOTO
Shotcreting · berm face
SITE PHOTO
Safety railing install