↑ THE HEADLINE · WEEK 20
WatchBehind plan; corrective actions in progress. Project tracks -1.91% against revised baseline; forecast handover slips by 10 days.
Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: 2nd Shotcrete Group not yet remobilized. Zero safety incidents this week.
FORECAST · COMPLETION
TARGET
Jun 24, 2026
FORECAST
Jul 4, 2026
BEHIND TARGET
+10 days
vs current 14-day pace
DAYS TO HANDOVER
38of 250 program-days
PROGRESS
75.4%
-1.91%
vs 77.3% planned
VARIANCE
-1.91%
−0.07
vs revised baseline
SAFETY
0
14d streak
incidents this wk · 5 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
0
PTD
5
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
39,368
8-hour workday + Overtime
SAFETY
NCRs Issued
THIS WK
0
PTD
4
Closed
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
5
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
⚠ ILLUSTRATIVE · WAITING ON MASTER SCHEDULE
TODAY · 75%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
21/33
CREW
Weather + crew
Clear, 31°C
31°
Clear · Hum Very High · Wind 9 km/h
RAIN-DAYS · MAY
0 rain days this month
CREW ON SITE
63% staffed
21of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 21 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 83.27%; Actual: 94.27%)
Slope Protection
tgt 69%50%-18.43%
5th Avenue - Trimming
26th Street - Drilling
Berm - Trimming, Wiremesh Installation, Shotcreting
Delivery of Materials - Soil Nail Rebars
Risks + open items
Watch-list
2nd Shotcrete Group not yet remobilized.
Watch · open
NCRs open
4
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
May 21
DPR-BGC_LUX-2026-018
77.33%
75.42%
-1.91%
Watch
›
May 20
DPR-BGC_LUX-2026-016
76.65%
75.10%
-1.55%
Watch
›
May 19
DPR-BGC_LUX-2026-015
75.98%
74.61%
-1.37%
Watch
›
May 18
DPR-BGC_LUX-2026-014
75.31%
74.81%
-0.50%
Watch
›
May 16
DPR-BGC_LUX-2026-013
74.03%
74.43%
+0.40%
On Track
›
May 15
DPR-BGC_LUX-2026-012
73.35%
73.96%
+0.61%
On Track
›
May 14
DPR-BGC_LUX-2026-011
72.67%
73.21%
+0.54%
On Track
›
From site, today
10 photos · Thu May 21 report

Dust Control

Delivery of Rebars

Excavation Works along 5th-26th

Wiremesh Installation along Berm near 26th

Hauling and Disposal

Shotcrete Team

Safety railing install