LLuxury SuperBlockBGC · 2025–2027
SYNC · LIVE
06:38 PHT
SharePoint · DailyReports
↑ THE HEADLINE · WEEK 20
Behind
Behind plan; corrective actions in progress. Project tracks -3.24% against revised baseline; forecast handover slips by 9 days.

Substructure phase. Daily output is sustained by the current contractor mobilisation; watch: Reinstallation of Valve on Damaged Waterline Pipe - Incident Report sent via email Zero safety incidents this week.

Substructure phase86% completeDay 233 / 2501 contractor delay · Day 3
FORECAST · COMPLETION
TARGET
Jun 28, 2026
FORECAST
Jul 7, 2026
BEHIND TARGET
+9 days
vs current 14-day pace
DAYS TO HANDOVER
17of 250 program-days
PROGRESS
86.0%
-3.24%
vs 89.2% planned
VARIANCE
-3.24%
−0.07
vs revised baseline
SAFETY
1
14d streak
incidents this wk · 5 PTD
HSEQ status
This week + project-to-date
SAFETY
Recordable Incident / Accident & Near Miss
THIS WK
1
PTD
5
Damaged Waterline Pipe
QUALITY
NCRs Issued
THIS WK
0
PTD
4
For Closing
QUALITY
Progress Inspection Reports
THIS WK
0
PTD
5
For Closing
ENVIRONMENTAL
Environmental Incident
THIS WK
0
PTD
1
Closed
SAFETY
Safety Manhours
THIS WK
0
PTD
44,268
8-hour workday
Progress trajectory · Daily
Plan vs actual + 28-day forecast · 30 reporting points
Actual Plan (rev. baseline) Forecast
65%70%75%80%85%90%BASELINE V2May 9May 21Jun 1Jun 11
Enabling works · programme
2 of 3 active · Site prep, bulk excavation and slope protection
⚠ ILLUSTRATIVE · WAITING ON MASTER SCHEDULE
TODAY · 86%
Site Prep + Mobilization100%
Bulk Excavation — Retail Block93%
Slope Protection (5th / 26th)48%
Contractor performance
Substructure phase · this week
We Enterprises & Contractors Inc.
Excavation, Slope, Hauling
29/33
CREW
Weather + crew
Clear, 33°C
33°
Clear · Hum Very High · Wind 20 km/h
RAIN-DAYS · JUN
4 rain days this month
CREW ON SITE
87% staffed
29of 33 planned
Today's work · vs target
We Enterprises & Contractors Inc. · 29 on site
Bulk Excavation of Retail Block (10 meters depth) [Target: 95.74%; Actual: 97.34%)
Slope Protection
tgt 84%72%-11.63%
5th Avenue - Wiremesh Installation, Soil Nail Installation
26th - Trimming
28th Street - Drilling, Plate Locking
Dewatering
Risks + open items
Watch-list
Reinstallation of Valve on Damaged Waterline Pipe - Incident Report sent via email
Watch · open
NCRs open
4
RFIs pending
0
QA / QC open
0
Recent daily reports
Last 7 reporting days
Date
Report
Plan
Actual
Var
Status
Jun 11
DPR-BGC_LUX-2026-035
89.20%
85.96%
-3.24%
Behind
Jun 10
DPR-BGC_LUX-2026-035
88.47%
85.62%
-2.85%
Behind
Jun 9
DPR-BGC_LUX-2026-034
87.74%
85.04%
-2.70%
Behind
Jun 8
DPR-BGC_LUX-2026-033
87.00%
84.36%
-2.64%
Behind
Jun 6
DPR-BGC_LUX-2026-032
85.54%
83.80%
-1.74%
Watch
Jun 5
DPR-BGC_LUX-2026-031
87.62%
83.16%
-4.46%
Behind
Jun 4
DPR-BGC_LUX-2026-030
86.81%
82.66%
-4.15%
Behind
From site, today
9 photos · Thu Jun 11 report
Slope Protection Along Berm at 28th
Slope Protection Along Berm at 28th
Excavated Area View along Berm at 28th
Excavated Area View along Berm at 28th
Excavated Area View from Berm along 26th
Excavated Area View from Berm along 26th
Shotcrete Crew Concrete Mixing
Shotcrete Crew Concrete Mixing
Slope Protection Along Berm at 26th
Slope Protection Along Berm at 26th
Slope Protection Along Berm at Ramp
Slope Protection Along Berm at Ramp
Safety railing install
Safety railing install